Wednesday, June 15, 2016

FLATIRON

We are pleased to advise that construction of FV Flatiron is progressing well.

At the end of May 2016 the majority of the transfer slab was poured, allowing for the basement and podium propping to be removed this month. The construction hoists are now being installed, which will allow for greater productivity on-site as the residential tower floors commence.

Brookfield Multiplex are on track to complete Flatiron in mid 2017.

Source: Gurner

Valley House

We are pleased to advise that construction of FV Valley House is progressing well.

At the end of May 2016 the majority of the transfer slab was poured, allowing for the basement and podium propping to be removed this month. The construction hoists are now being installed, which will allow for greater productivity on-site as the residential tower floors commence.

Brookfield Multiplex are on track to complete Valley House in mid 2017.

News picture.

Source: Gurner

ARTHOUSE - CONSTRUCTION UPDATE JUNE 2016

As a valued Mirvac purchaser, we are very pleased to advise that Art House, South Brisbane is now 100% sold.

Construction has embarked on an exciting time for the project, with pouring of the first residential level, level 8, slabs nearing completion.

This month will also see the installation of the external facade with wrapping motif and varied spandrel forms, the start to Art House really coming to life on the South Brisbane skyline.

Once the facade is installed, trades will be able to commence finishes on the completed floors.

Our neighbouring project, Lucid, is commence construction works in early June now that demolition is complete.

Source: Mirvac Queensland